Near-Critical Path is close in duration to the critical path. Something could happen that shortens the critical path or lengthens the near-critical path to the point where the near-critical path becomes critical. The closer in length the near-critical path and critical paths are, the more risk the project has. You need to focus time and effort monitoring and controlling activities on both the critical and near-critical paths so there is no delay to project completion.