Plan Risk Management is the process of defining how risk management activities will be conducted throughout the project lifecycle. It is a key process within the Risk Management Knowledge Area and part of the Planning Process Group. The primary output of this process is the Risk Management Plan, which provides the foundation for identifying, analyzing, and responding to risks effectively.

This article explains the inputs, tools and techniques, and outputs of the Plan Risk Management process. It also provides practical examples and outlines the recommended structure of the Risk Management Plan, offering clear guidance for project managers, risk analysts, and other stakeholders.


Inputs to Plan Risk Management

  1. Project Management Plan:
    • Definition: The overarching plan integrating all subsidiary plans, including the risk management strategy.
    • Purpose: Provides information on scope, schedule, cost, and other elements that impact risk planning.
    • Example: A construction project’s management plan includes a tight schedule, indicating potential risks of delays.
  2. Project Charter:
    • Definition: A high-level document authorizing the project and outlining its objectives, constraints, and assumptions.
    • Purpose: Helps identify high-level risks and stakeholder expectations related to risk.
    • Example: A charter for an IT project mentions a fixed budget, highlighting financial risks.
  3. Stakeholder Register:
    • Definition: A document that identifies all stakeholders, their roles, and their impact on the project.
    • Purpose: Helps identify stakeholders who can contribute to or be impacted by risks.
    • Example: A large infrastructure project’s register identifies government officials as key stakeholders, requiring regulatory risks to be addressed.
  4. Project Documents:
    • Definition: Includes project communications and other relevant documents that inform risk planning.
    • Purpose: Provides insights into potential risks based on project details.
    • Example: Communications reveal that supplier delays have occurred in similar past projects.
  5. Enterprise Environmental Factors (EEFs):
    • Definition: External factors such as market conditions, regulations, or organizational culture.
    • Purpose: Influences risk management planning based on external constraints.
    • Example: Economic instability increases financial risks for an international project.
  6. Organizational Process Assets (OPAs):
    • Definition: Internal resources, policies, and lessons learned from previous projects.
    • Purpose: Offers historical data and templates to guide risk planning.
    • Example: A manufacturing company uses a risk matrix template from a past project to streamline planning.

Tools and Techniques for Plan Risk Management

  1. Analytical Techniques:
    • Definition: Techniques used to assess potential risks and evaluate risk tolerance.
    • Purpose: Helps define approaches to risk management.
    • Example: A quantitative analysis determines the probability of exceeding the budget in a software project.
  2. Expert Judgment:
    • Definition: Involves consulting subject matter experts to assess risks and develop strategies.
    • Purpose: Ensures realistic and practical risk management approaches.
    • Example: A senior project manager provides insights on risks associated with a new technology.
  3. Meetings:
    • Definition: Collaborative sessions with stakeholders to gather inputs for risk planning.
    • Purpose: Facilitates consensus on risk approaches and roles.
    • Example: A kickoff meeting includes discussions on potential risks and mitigation strategies.

Output of Plan Risk Management

  1. Risk Management Plan:
    • Definition: A document that outlines how risk management activities will be conducted.
    • Purpose: Provides a roadmap for identifying, analyzing, monitoring, and responding to risks.
    • Example: Specifies that a weekly risk review meeting will be conducted with the core team.

Recommended Content of the Risk Management Plan

  1. Risk Management Approach:
    • Defines the methodology, tools, and techniques for managing risks.
    • Example: Use of Monte Carlo simulation for quantitative risk analysis.
  2. Roles and Responsibilities:
    • Assigns ownership for specific risk-related tasks.
    • Example: The project manager oversees risk monitoring, while team leads report identified risks.
  3. Risk Categories:
    • Defines categories of risks (e.g., technical, financial, external).
    • Example: A healthcare project identifies regulatory risks under “External Risks.”
  4. Risk Tolerance:
    • Establishes the organization’s or stakeholders’ risk thresholds.
    • Example: A company’s risk tolerance allows for a ±10% variance in project cost.
  5. Risk Identification Process:
    • Details how risks will be identified throughout the project.
    • Example: Regular brainstorming sessions during sprint planning.
  6. Risk Analysis Methodology:
    • Specifies whether qualitative, quantitative, or both analysis methods will be used.
    • Example: Qualitative analysis for early-stage risks, followed by quantitative analysis for high-impact risks.
  7. Risk Response Planning:
    • Outlines the strategies for mitigating, avoiding, transferring, or accepting risks.
    • Example: Insurance is purchased to transfer financial risk.
  8. Risk Monitoring and Reporting:
    • Details how risks will be tracked, reviewed, and reported.
    • Example: Weekly risk status reports to stakeholders.
  9. Funding for Risk Activities:
    • Allocates contingency reserves for addressing identified risks.
    • Example: A 5% budget reserve for unforeseen risks.
  10. Risk Escalation Process:
    • Defines how unresolved risks will be escalated.
    • Example: Escalation to the steering committee for risks impacting project timelines by over 15%.

Practical Examples of Plan Risk Management

  1. Construction Project:
    • Scenario: Building a high-rise apartment.
    • Plan Content:
      • Categorizes risks as environmental, technical, and regulatory.
      • Uses qualitative analysis for early-stage risks.
      • Conducts monthly risk reviews.
  2. Software Development:
    • Scenario: Launching a mobile app.
    • Plan Content:
      • Identifies risks like delayed integration with APIs.
      • Assigns developers to report technical risks weekly.
      • Allocates contingency for unexpected technical failures.
  3. Event Planning:
    • Scenario: Organizing a corporate conference.
    • Plan Content:
      • Lists vendor and logistical risks.
      • Uses a risk matrix to assess likelihood and impact.
      • Prepares backup plans for key suppliers.

Summary Table: Plan Risk Management

Category Details Example
Inputs Project Management Plan, Project Charter, Stakeholder Register, EEFs, OPAs A project charter identifies fixed-budget constraints
Tools and Techniques Analytical Techniques, Expert Judgment, Meetings Quantitative risk analysis using Monte Carlo simulations
Output Risk Management Plan Weekly risk monitoring meetings defined in the plan

Conclusion

Plan Risk Management lays the groundwork for managing risks effectively throughout the project lifecycle. By leveraging inputs like the stakeholder register and project charter, applying techniques such as expert judgment and analytical methods, and producing a comprehensive Risk Management Plan, project teams can proactively address uncertainties. This structured approach minimizes disruptions and enhances the likelihood of project success.

Knowledge Area

Risk Management

Process Group

Planning

Plan Risk Management Inputs

  • Project Management Plan
  • Project Communications
  • Project Charter
  • Stakeholder Register
  • Enterprise Environmental Factors
  • Organizational Process Assets

Plan Risk Management Tools and Techniques

  • Analytical Techniques
  • Expert Judgement
  • Meetings

Plan Risk Management Outputs

  • Risk Management Plan
Last Update: December 3, 2024
July 27, 2017 13 Project VictorRisk Management
Total 0 Votes
0

Tell us how can we improve this post?

+ = Verify Human or Spambot ?

Add A Knowledge Base Question !

You will receive an email when your question will be answered.

+ = Verify Human or Spambot ?

Add A Knowledge Base Question !

You will receive an email when your question will be answered.

+ = Verify Human or Spambot ?

Back To Top